ACCA Strategic Professional · Advanced Performance Management · Performance improvement models and techniques
Halden Appliances uses target costing for a new blender. Target selling price is $80 and target margin is $20. The current cost is $68 per unit, made up of components $40, assembly $18 and other costs $10. Management ranks function value by customer survey and finds that the motor, which is 50% of customer-perceived value, currently accounts for $15 of the $68 cost. Applying value engineering so cost is proportional to customer-perceived value across the total target cost, which conclusion is correct?
The motor is under-costed by $15 relative to its value share, so reductions should focus on other functions. Target cost is $80 minus $20, which is $60. A 50% value share justifies $30 for the motor, versus $15 currently, while the other functions cost $53 against $30 allowed.
- AThe motor is over-costed by $15 relative to its value share
- BThe motor is under-costed by $15 relative to its value share, so it should be given a $30 budget
- CThe motor is under-costed by $15 relative to its value share, so cost reduction should concentrate on it
- DThe motor is under-costed by $15 relative to its value share, so cost reduction should concentrate on other functionsCorrect
Explanation
Target cost = 80 - 20 = $60. Motor's value share of 50% implies an allowable cost of $30. Current cost is $15, so it is under-costed by $15. Savings of $8 (68 - 60) must come from other functions, whose current cost is $53 against an allowable $30.
Did you get it right without looking?
One question tells you little. A timed set on Performance improvement models and techniques shows your real accuracy, how long you take and where you lose marks.
More Performance improvement models and techniques questions
- Marlow Co has a throughput accounting ratio (TPAR) calculation for its main product. Throughput per factory hour is $45 and total factory co…
- Ostrava Metals is introducing a just-in-time (JIT) system as part of a lean programme. Which outcome is most consistent with successful JIT …
- Kestrel Components is considering a BPR project. Which of the following is the most likely cause of the project failing to deliver its expec…
- Brandt Electronics uses the Six Sigma DMAIC cycle to tackle high rates of faulty circuit boards. The team has defined the problem, set up da…
- Harbor Relief, a charity, measures its performance only by the percentage of donations spent directly on programmes. Trustees argue this is …
- Calder Foods produces ready meals. Quality costs last year were: staff training in quality procedures $40,000; inspection of incoming ingred…