ACCA Strategic Professional · Advanced Performance Management · Performance improvement models and techniques
Ostrava Metals is introducing a just-in-time (JIT) system as part of a lean programme. Which outcome is most consistent with successful JIT implementation?
Lower inventory holding costs is the outcome consistent with JIT. JIT is a pull system that buys and produces only against actual demand, so it depends on reliable suppliers and short set-up times. Large safety stocks, big batches and forecast-driven production are features of push systems that JIT seeks to remove.
- ALower inventory holding costs, supported by reliable suppliers and short set-up timesCorrect
- BHigher safety stocks to guard against supplier delays
- CLarger production batches to spread set-up costs
- DProduction scheduled on forecast demand to keep machines fully utilised
Explanation
JIT produces and purchases only as needed, so inventory falls, which needs reliable suppliers, quick set-ups and a pull system driven by actual demand. Higher safety stock, larger batches and forecast-driven production are all push-system features that contradict JIT.
Did you get it right without looking?
One question tells you little. A timed set on Performance improvement models and techniques shows your real accuracy, how long you take and where you lose marks.
More Performance improvement models and techniques questions
- Halden Appliances uses target costing for a new blender. Target selling price is $80 and target margin is $20. The current cost is $68 per u…
- Verdant Insurance is re-engineering its claims handling. Currently a claim is passed sequentially between a registration clerk, an assessor,…
- Pinnacle Bank's retail division has run a kaizen programme for three years, with staff suggesting small improvements to loan processing. Man…
- Harbour Logistics Ltd's order-to-delivery process passes through nine departments, each of which checks and approves the order before handin…
- Kestrel Ltd makes three products using a single machine that is the only bottleneck. Product X sells for $50 with material cost $20 and uses…
- Verano Ltd has adopted TQM. A divisional manager proposes the following: (1) appoint a quality inspector to check all output at the end of t…