Himalaya Cement Ltd. is constructing a kiln (qualifying asset) financed by a specific loan of Rs 1,20,00,000 at 12% p.a. Active development was suspended for 3 months, from 1 July 2025 to 30 September 2025, because of a labour dispute, which is an extended period not necessary for the asset's construction. Work otherwise continued through the year ended 31 March 2026. What amount of interest should be capitalised, and what is the treatment of the rest?
Rs 10,80,000 is capitalised and Rs 3,60,000 is charged to profit and loss. AS 16 requires suspending capitalisation during extended periods when active development is interrupted, so interest for the three idle months is expensed, while interest for the other nine months of the Rs 14,40,000 annual cost is capitalised.
- ARs 14,40,000 capitalised; nothing expensed
- BRs 10,80,000 capitalised; Rs 3,60,000 charged to profit and lossCorrect
- CRs 10,80,000 capitalised; Rs 3,60,000 deferred as prepaid expense
- DRs 3,60,000 capitalised; Rs 10,80,000 charged to profit and loss
Explanation
Annual interest = 1,20,00,000 x 12% = Rs 14,40,000. Capitalisation is suspended during extended periods when active development is interrupted, so the 3 months' interest of Rs 3,60,000 is expensed. Capitalised amount is 9/12 x 14,40,000 = Rs 10,80,000.
Did you get it right without looking?
One question tells you little. A timed set on AS 16 Borrowing Costs shows your real accuracy, how long you take and where you lose marks.
More AS 16 Borrowing Costs questions
- Vaishnavi Infra Ltd borrowed Rs 2,00,00,000 at 10% p.a. specifically to construct a warehouse (a qualifying asset). Construction ran for the…
- Godavari Power Ltd has no specific borrowing for a qualifying asset but has two general borrowings outstanding all year 2025-26: ₹2 crore at…
- Himalaya Textiles Ltd is considering four items for the year ended 31 March 2027. Which one is a qualifying asset under AS 16 (Borrowing Cos…
- Vihaan Steel Ltd. is constructing a blast furnace, a qualifying asset. Active development was suspended for 4 months because of a prolonged …
- Sundaram Heavy Engineering Ltd is building a fabrication plant, a qualifying asset, financed only by general borrowings outstanding all year…
- Sundaram Textiles Ltd. borrowed Rs 2,00,000 at 12% p.a. specifically to build a warehouse. The construction took 2 years and 3 months to com…