CA Intermediate · Advanced Accounting · AS 16 Borrowing Costs
Sundaram Heavy Engineering Ltd is building a fabrication plant, a qualifying asset, financed only by general borrowings outstanding all year: a ₹50,00,000 term loan at 10% p.a. and ₹30,00,000 debentures at 12% p.a. Expenditure on the plant was ₹24,00,000 on 1 April and ₹12,00,000 on 1 October. For the year ended 31 March, active development was suspended for an extended period of two months because of a dispute with the contractor. Assuming no other interruptions, what amount of borrowing cost should be capitalised?
₹2,58,000 is capitalised. The weighted average rate is 10.75%. Capitalisation is suspended for two months, so the ₹24 lakh outlay counts for 10 months, giving ₹2,15,000, and the ₹12 lakh outlay for 4 months, giving ₹43,000. The two amounts together equal ₹2,58,000.
- A₹2,58,000Correct
- B₹3,22,500
- C₹2,64,000
- D₹8,60,000
Explanation
Capitalisation rate = (5,00,000 + 3,60,000) / 80,00,000 = 10.75%. After excluding the two-month suspension, the first outlay is financed for 10 months: 24,00,000 × 10.75% × 10/12 = ₹2,15,000. The second is financed for 6 − 2 = 4 months: 12,00,000 × 10.75% × 4/12 = ₹43,000. Total is ₹2,58,000. Ignoring the suspension gives ₹3,22,500, and using a simple average rate of 11% gives ₹2,64,000.
Did you get it right without looking?
One question tells you little. A timed set on AS 16 Borrowing Costs shows your real accuracy, how long you take and where you lose marks.
More AS 16 Borrowing Costs questions
- Meena Textiles Ltd. began constructing a new factory on 1 April 2025 using a specific loan of ₹50,00,000 at 9% p.a. Active development was s…
- Kaveri Infra Ltd. is building a bridge, a qualifying asset. Expenditure was ₹60,00,000 on 1 April 2025 and ₹40,00,000 on 1 October 2025, fun…
- Konark Engineering Ltd took a term loan of Rs 10,00,00,000 at 12% p.a. on 1 April 2025 solely to build a new plant. Physical construction wa…
- Nilgiri Power Ltd. is constructing a plant that is a qualifying asset. Part of the plant, Unit A, was completed and put to use on 1 January …
- Vindhya Cements Ltd. is building a plant, which is a qualifying asset. Construction started on 1 April 2025. Because of a labour dispute, ac…
- Sundaram Textiles Ltd. took a specific term loan of Rs 2,00,00,000 at 10% p.a. on 1 April 2025 to construct a new weaving unit, which is a q…