CA Intermediate · Advanced Accounting · AS 7 Construction Contracts
Himalaya Projects Ltd has a contract with an initial fixed price of ₹1,000 lakh. Total estimated cost is ₹800 lakh throughout. In year 1, costs incurred were ₹200 lakh, so revenue of ₹250 lakh was recognised. In year 2, cumulative costs incurred are ₹480 lakh. During year 2, the customer agreed in principle to an incentive payment of ₹50 lakh for early completion; it is probable the performance standards will be met and the amount can be measured reliably. Stage of completion is on the cost proportion basis. What revenue should be recognised for year 2?
Year 2 revenue is ₹380 lakh. The probable and measurable incentive raises contract revenue to ₹1,050 lakh. Cumulative stage of completion is 480 divided by 800, or 60 per cent, giving ₹630 lakh cumulative revenue. Deducting ₹250 lakh recognised in year 1 leaves ₹380 lakh.
- A₹380 lakhCorrect
- B₹350 lakh
- C₹630 lakh
- D₹300 lakh
Explanation
The incentive is included in contract revenue because the AS 7 conditions are met, so total revenue is 1,000 + 50 = ₹1,050 lakh. Stage of completion at end of year 2 = 480/800 = 60%, giving cumulative revenue of ₹630 lakh. Year 2 revenue = 630 − 250 = ₹380 lakh. Ignoring the incentive gives ₹350 lakh, and failing to deduct year 1 revenue gives ₹630 lakh.
Did you get it right without looking?
One question tells you little. A timed set on AS 7 Construction Contracts shows your real accuracy, how long you take and where you lose marks.
More AS 7 Construction Contracts questions
- Himalaya Projects Ltd has a fixed-price contract of ₹200 lakh with total estimated contract cost of ₹150 lakh. Costs incurred to date are ₹9…
- Meridian Infra Ltd is building a flyover for a state government under a construction contract. Its accountant is listing the costs for the c…
- Malwa Engineers undertakes a contract. Which of the following costs would be excluded from contract costs under AS 7 because they cannot be …
- Kaveri Infra Ltd. has a fixed-price contract of ₹50 lakh. At the end of the first year, costs incurred to date are ₹36 lakh and the estimate…
- Shivalik Constructions Ltd has a fixed price contract of ₹1,000 lakh. At the year end, costs incurred to date are ₹480 lakh, which include ₹…
- Narmada Projects has a fixed price contract of Rs 200 lakh. Year 1: costs incurred Rs 60 lakh, estimated further cost Rs 120 lakh. Year 2: c…