CA Intermediate · Advanced Accounting · AS 7 Construction Contracts
Kaveri Infra Ltd. has a fixed-price contract of ₹50 lakh. At the end of the first year, costs incurred to date are ₹36 lakh and the estimated further cost to complete is ₹24 lakh. Assume the percentage of completion is measured by cost to cost and the price is not expected to change. What amount of loss should be recognised in the Statement of Profit and Loss for the first year?
The loss to be recognised is ₹10 lakh. Total estimated cost is ₹60 lakh against a contract price of ₹50 lakh, and AS 7 requires the entire expected loss to be recognised immediately as an expense, not in proportion to the stage of completion.
- A₹10 lakhCorrect
- B₹6 lakh
- C₹4 lakh
- DNil, as the loss will be recognised only when the contract is completed
Explanation
Total estimated cost = 36 + 24 = ₹60 lakh against price ₹50 lakh, so the expected loss is ₹10 lakh. Under AS 7 an expected loss on a contract is recognised as an expense immediately, irrespective of the stage of completion. Recognising only 60% of the loss (₹6 lakh) is wrong because the full loss is charged at once.
Did you get it right without looking?
One question tells you little. A timed set on AS 7 Construction Contracts shows your real accuracy, how long you take and where you lose marks.
More AS 7 Construction Contracts questions
- Sagar Builders has a contract with an original fixed price of ₹200 lakh. During the second year, the customer approved a variation adding ₹2…
- Meridian Infra Ltd is building a flyover for a state government under a construction contract. Its accountant is listing the costs for the c…
- Himalaya Projects Ltd has a contract with an initial fixed price of ₹1,000 lakh. Total estimated cost is ₹800 lakh throughout. In year 1, co…
- Shivalik Constructions Ltd has a fixed price contract of ₹1,000 lakh. At the year end, costs incurred to date are ₹480 lakh, which include ₹…
- Rajdhani Constructions Ltd has a fixed-price contract of ₹80 lakh. At the end of Year 1, costs incurred were ₹20 lakh and estimated further …
- Vindhya Infra Ltd has a fixed price contract of ₹80,00,000. At the end of Year 1: costs incurred ₹30,00,000, estimated further cost to compl…