In a factory, the wages paid to workers for the time they were idle because of a power failure that lasted two hours are best treated in cost accounting as:

Wages paid for idle time caused by a power failure are abnormal idle time cost, and they are charged to the Costing Profit and Loss Account, because the cause is uncontrollable and abnormal and so should not be absorbed into product or job costs.

  1. ANormal idle time cost, charged to factory overheads
  2. BAbnormal idle time cost, charged to Costing Profit and Loss AccountCorrect
  3. CDirect wages charged to the job being worked on
  4. DOvertime premium charged to the specific job

Explanation

Idle time due to causes like power failure is beyond management control and not expected in normal operations, so it is abnormal idle time. Its cost is not loaded on products but written off to the Costing Profit and Loss Account. Treating it as normal idle time would wrongly inflate overheads.