CA Intermediate · Cost and Management Accounting · Employee Cost and Direct Expenses
Meenakshi Textiles pays a skilled worker Rs 120 per hour for a 48-hour week. Normal week is 40 hours. Overtime beyond 40 hours is paid at double the normal rate. In that week 8 overtime hours were worked, caused by a rush order from a specific customer, Arjun Exports, at its request. Which treatment and amount of overtime premium is correct for cost accounting?
The premium is Rs 960, charged directly to Arjun Exports' job. Overtime pay at double rate is 8 x 240 = Rs 1,920, of which the normal portion is 8 x 120 = Rs 960 and the rest is premium. Since the customer requested the rush, the premium belongs to that job.
- APremium Rs 960 charged to Arjun Exports' job as direct costCorrect
- BPremium Rs 960 charged to factory overheads
- CPremium Rs 1,920 charged to the job of Arjun Exports
- DPremium Rs 1,920 charged to costing profit and loss account
Explanation
Overtime premium = extra over normal rate = 8 x (240 - 120) = Rs 960. When overtime is at the customer's special request, the premium is charged to that customer's job. Rs 1,920 is the whole overtime pay at double rate, not just the premium. Overheads treatment applies when overtime is due to general pressure of work.
Did you get it right without looking?
One question tells you little. A timed set on Employee Cost and Direct Expenses shows your real accuracy, how long you take and where you lose marks.
More Employee Cost and Direct Expenses questions
- A factory worker at Kalyani Engineering is paid a basic wage of Rs 600 per day plus dearness allowance. The company's cost accountant is cla…
- Kaveri Textiles pays a worker on the Rowan plan. Time rate is Rs 30 per hour, standard time is 60 hours, and actual time taken is 45 hours. …
- Sharma Textiles pays a worker under the Halsey premium plan. Standard time for a job is 40 hours, the time taken is 30 hours, the hourly rat…
- Which of the following is an example of idle time in employee cost accounting?
- Ganga Components employs 400 workers on average in a year. During the year 60 workers left and 20 were replaced; additionally 40 new workers…
- Which of the following is a standard, named method of remunerating labour under which the wage rate per unit of output is fixed and the work…