CMA Final · Strategic Cost Management · Simulation
In a Monte Carlo simulation of a queue, inter-arrival times are 2 minutes for 00-49 and 4 minutes for 50-99. Random numbers for three successive arrivals are 72, 18, 55. If the first customer arrives at time 0 and the next three arrive after these gaps, what is the arrival time of the third arriving customer after the first?
The arrival time is 10 minutes. The numbers 72, 18 and 55 give gaps of 4, 2 and 4 minutes, and adding them cumulatively gives arrivals at 4, 6 and 10 minutes.
- A8 minutes
- B10 minutesCorrect
- C6 minutes
- D12 minutes
Explanation
72 gives 4 min, 18 gives 2 min, 55 gives 4 min. Cumulative arrival times after the first are 4, 6, 10. The third arriving customer after the first arrives at 10 minutes.
Did you get it right without looking?
One question tells you little. A timed set on Simulation shows your real accuracy, how long you take and where you lose marks.
More Simulation questions
- Daily demand for a product is simulated with these random-number ranges: 00-29 = 10 units, 30-79 = 20 units, 80-99 = 30 units. Random number…
- In a simulation of machine breakdowns for an Ahmedabad plant, the simulated repair times for five breakdowns are 2, 4, 3, 5 and 1 hours. If …
- A Chennai retailer simulates daily demand: 2 units (prob 0.3), 3 units (prob 0.5), 4 units (prob 0.2). Random numbers 00-99 are used. Openin…
- A linear congruential generator uses X(n+1) = (5 × X(n) + 3) mod 16, with seed X(0) = 7. What is the third generated number, X(3)?
- In a single-server queue simulation at a Pune service counter, four customers arrive at minutes 0, 2, 3 and 8, with service times of 4, 3, 2…
- In a Monte Carlo simulation of daily demand for a Pune bakery, the cumulative probabilities are: 10 loaves 0.20; 20 loaves 0.50; 30 loaves 0…