FRM Part I · FRM Exam Part I · Simulation and Bootstrapping
In a Monte Carlo simulation to estimate a 99% one-day VaR, an analyst generates 1,000 simulated portfolio P&L outcomes and sorts them from worst to best. Using the simple order-statistic approach, which outcome is the 99% VaR estimate?
The 99% VaR is the 10th worst simulated loss. With 1,000 outcomes, the worst 1 percent equals ten observations, so the loss at that cutoff in the sorted P&L distribution is the estimate.
- AThe 10th worst lossCorrect
- BThe 1st worst loss
- CThe 99th worst loss
- DThe 100th worst loss
Explanation
A 99% VaR leaves 1% of outcomes in the tail. With 1,000 trials, 1% is 10 observations, so the 10th worst loss is the cutoff. The 99th worst corresponds to a 90.1% confidence level.
Did you get it right without looking?
One question tells you little. A timed set on Simulation and Bootstrapping shows your real accuracy, how long you take and where you lose marks.
More Simulation and Bootstrapping questions
- A bank uses a bootstrap with historical returns to estimate the standard error of a 99% VaR estimate. Which statement about the effect of th…
- A stock price follows geometric Brownian motion with S0 = 100, drift mu = 8% per year, volatility sigma = 20% and the simulation uses a one-…
- A risk manager simulates 10,000 independent one-day portfolio losses and estimates the mean loss as 2.0 with sample standard deviation 15.0.…
- A simulation of a portfolio's one-day loss uses 10,000 independent draws and estimates the mean loss as 2.0 million with sample standard dev…
- An analyst has a sample of 50 independent daily returns and wants to estimate the standard error of the sample median using the bootstrap. W…
- A Monte Carlo analyst compares a simulation using antithetic variates with one using the same number of independent draws. Which statement b…