FRM Part I · FRM Exam Part I · Simulation and Bootstrapping

In a Monte Carlo simulation to estimate a 99% one-day VaR, an analyst generates 1,000 simulated portfolio P&L outcomes and sorts them from worst to best. Using the simple order-statistic approach, which outcome is the 99% VaR estimate?

The 99% VaR is the 10th worst simulated loss. With 1,000 outcomes, the worst 1 percent equals ten observations, so the loss at that cutoff in the sorted P&L distribution is the estimate.

  1. AThe 10th worst lossCorrect
  2. BThe 1st worst loss
  3. CThe 99th worst loss
  4. DThe 100th worst loss

Explanation

A 99% VaR leaves 1% of outcomes in the tail. With 1,000 trials, 1% is 10 observations, so the 10th worst loss is the cutoff. The 99th worst corresponds to a 90.1% confidence level.