CMA Intermediate · Operations Management and Strategic Management · Operations Planning
In capacity planning, the ratio of actual output achieved to the effective capacity of a facility is called:
The ratio of actual output to effective capacity is efficiency. Utilisation compares actual output with design capacity, so it is a different measure. Design capacity is the maximum possible output under ideal conditions, not a ratio of output.
- AUtilisation
- BEfficiencyCorrect
- CDesign capacity
- DSafety capacity
Explanation
Efficiency = actual output / effective capacity. Utilisation instead compares actual output with design capacity, so it is the key distractor. Design capacity is the maximum theoretical output and safety capacity is not the ratio asked for.
Did you get it right without looking?
One question tells you little. A timed set on Operations Planning shows your real accuracy, how long you take and where you lose marks.
More Operations Planning questions
- A packaged-snacks company in Pune wants to forecast next quarter's sales of a new flavour for which no sales history exists. It decides to c…
- Sundaram Auto Parts has a design capacity of 1,200 units per week and an effective capacity of 1,000 units per week. Actual output last week…
- In the hierarchy of operations planning, which of the following correctly places the Master Production Schedule (MPS) relative to aggregate …
- In operations planning, which of the following best describes the main purpose of aggregate planning?
- A manufacturer arranges its machines so that all lathes are in one section, all drilling machines in another and all milling machines in a t…
- Kaveri Textiles uses a simple moving average of the last three months to forecast demand. Sales for the last three months were 420, 450 and …