CMA Intermediate · Operations Management and Strategic Management · Operations Planning
In the hierarchy of operations planning, which of the following correctly places the Master Production Schedule (MPS) relative to aggregate planning and material requirements planning (MRP)?
The MPS disaggregates the aggregate plan into specific end items and time periods, and it feeds MRP. Aggregate planning comes first at family level, the MPS follows at product level, and MRP then derives component and material requirements from the MPS.
- AMPS disaggregates the aggregate plan into specific end items and timings, and serves as the main input to MRPCorrect
- BMPS is prepared after MRP to decide the quantity of raw materials to be ordered
- CMPS is prepared before aggregate planning and fixes the total workforce for the year
- DMPS replaces the aggregate plan and is prepared in monthly totals for product families
Explanation
Aggregate planning works with product families over a medium-term horizon. The MPS breaks this plan into specific end items by period. MRP then uses the MPS to compute component and material requirements, so the MPS sits between the two.
Did you get it right without looking?
One question tells you little. A timed set on Operations Planning shows your real accuracy, how long you take and where you lose marks.
More Operations Planning questions
- A firm compares three sites for a plant using the factor rating method. Weights: labour availability 0.50, proximity to market 0.30, infrast…
- A plant in Pune has a design capacity of 1,000 units per day and an effective capacity of 800 units per day. Actual output is 640 units per …
- In the hierarchy of operations planning, which decision is classified as a long-range (strategic) operations planning decision rather than a…
- A Jaipur textile unit uses single exponential smoothing with alpha = 0.3. Its forecast for the last month was 200 units and the actual deman…
- A plant with fixed costs of Rs 6,00,000 per year and variable cost of Rs 150 per unit is compared with another plant with fixed costs of Rs …
- In capacity planning, the ratio of actual output achieved to the effective capacity of a facility is called: