IAI Actuarial Core Principles · Economic Modelling · Run-off triangles
In practice, the latest diagonal of a triangle for a long-tailed liability class shows that all accident years have been fully developed to development year 5, but claims are known to continue beyond that. What is the appropriate way to deal with this under chain ladder?
The actuary should apply a tail factor greater than one, derived from external benchmark data or an extrapolated curve, to the latest cumulative claims. The triangle has no information beyond development year 5, so ignoring the tail would understate ultimate claims and reserves.
- ASet all future reserves to zero because the triangle is complete
- BUse only the first development year factor for all later periods
- CApply a tail factor greater than one, based on external data or a fitted curve, to the latest cumulative claimsCorrect
- DRemove the oldest accident year and recalculate all factors
- Replace cumulative claims with incurred claim counts
Explanation
A triangle only contains observed development; when claims continue beyond the last observed year, a tail factor above one, estimated from external benchmarks or an extrapolated curve, is needed to estimate ultimate claims. Setting reserves to zero would understate liabilities.
Did you get it right without looking?
One question tells you little. A timed set on Run-off triangles shows your real accuracy, how long you take and where you lose marks.
More Run-off triangles questions
- For an immature accident year, cumulative incurred claims are Rs 40 lakh, the incurred development factor to ultimate is 2.0, premium is Rs …
- Which feature of claims data most directly makes the basic chain ladder method unreliable when applied to a run-off triangle?
- A chain ladder projection is performed on a cumulative claims triangle in which the latest accident year has unusually large early claims du…
- An insurer writes a motor portfolio for accident year 2024 with earned premium of Rs 50 crore. Its prior expectation of the ultimate loss ra…
- In a cumulative run-off triangle of paid claims, rows are accident years and columns are development years. Which statement best describes w…
- In the inflation-adjusted chain ladder method applied to a cumulative or incremental claims run-off triangle, what is the first step before …