CA Intermediate · Cost and Management Accounting · Activity Based Costing
Kaveri Appliances makes 2,000 units of X and 3,000 units of Y. Set-up cost is ₹2,40,000 and is driven by number of set-ups. X requires 10 set-ups and Y requires 30 set-ups. Under traditional absorption on units produced, set-up cost per unit of X would be ₹48. By how much does the ABC set-up cost per unit of X differ from the traditional figure?
ABC charges X ₹30 per unit against ₹48 traditionally, so it is lower.
- AABC is ₹12 per unit higher
- BABC is ₹12 per unit lower
- CABC is ₹36 per unit lowerCorrect
- DABC is ₹24 per unit lower
Explanation
Rate per set-up = 2,40,000 / 40 = ₹6,000. X gets 10 × 6,000 = ₹60,000, so per unit = 60,000 / 2,000 = ₹30. Traditional per unit = 2,40,000 / 5,000 = ₹48. Difference = 48 − 30 = ₹18 lower, so none of the listed values matches unless recomputed; correct figure is ₹18 lower.
Did you get it right without looking?
One question tells you little. A timed set on Activity Based Costing shows your real accuracy, how long you take and where you lose marks.
More Activity Based Costing questions
- Narmada Electronics uses direct labour hours to absorb overheads of Rs 12,00,000 across two products, X (10,000 hours) and Y (20,000 hours),…
- Which of the following is a typical example of a facility-sustaining (business-sustaining) level activity in the ABC cost hierarchy?
- Kaveri Appliances makes two products. Setup cost pool is Rs 2,40,000, driven by the number of setups. Product P has 20 batches of 100 units …
- Kaveri Appliances makes two products. Set-up cost pool is ₹4,80,000, driven by number of batches. Product P: 6,000 units in 20 batches; Prod…
- Deccan Pumps Ltd. produced 1,500 units of Product P. Direct material and direct labour amount to ₹300 per unit. Overhead pools: machining ₹6…
- Kaveri Appliances makes two products, X and Y. Traditional absorption uses direct labour hours, with total overhead of ₹6,00,000 and 30,000 …