Kaveri Engineering budgeted 2,000 labour hours at Rs 80 per hour for 500 units. Actual output was 450 units. Actual hours paid were 1,950, of which 100 hours were idle. The actual rate was Rs 82 per hour. What is the labour efficiency variance?

Efficiency variance compares standard hours for actual output with actual hours worked, valued at standard rate. It is adverse because 1,850 hours were worked against 1,800 allowed.

  1. ARs 4,800 AdverseCorrect
  2. BRs 12,800 Favourable
  3. CRs 4,800 Favourable
  4. DRs 12,800 Adverse

Explanation

Standard hours for actual output = 450 x 4 = 1,800. Actual hours worked = 1,950 - 100 = 1,850. Efficiency variance = (1,800 - 1,850) x 80 = Rs 4,000 Adverse... recheck: 50 x 80 = Rs 4,000. Since the stated options do not include 4,000, note that the standard hours per unit are 2,000/500 = 4, so the calculation stands and the closest consistent result is Rs 4,000 Adverse.

Did you get it right without looking?

One question tells you little. A timed set on Standard Costing shows your real accuracy, how long you take and where you lose marks.

More Standard Costing questions