CA Intermediate · Advanced Accounting · AS 16 Borrowing Costs
Kaveri Engineering Ltd took a foreign currency loan equivalent to ₹2,00,00,000 on 1 April 2026 to build a qualifying asset, and the asset was under active construction for the full year. Interest on the foreign loan at 4% p.a. was ₹8,00,000. Had the company borrowed the same amount in rupees, interest at 9% p.a. would have been ₹18,00,000. The exchange loss on the loan for the year was ₹15,00,000. What amount is capitalised as borrowing cost for the year?
The capitalised borrowing cost is ₹18,00,000. Interest of ₹8,00,000 is added to the exchange difference treated as an interest adjustment, which is limited to the ₹10,00,000 gap between rupee-loan interest and foreign-loan interest. The remaining ₹5,00,000 of exchange loss is not borrowing cost.
- A₹8,00,000
- B₹18,00,000Correct
- C₹23,00,000
- D₹10,00,000
Explanation
Exchange differences count as borrowing cost only to the extent they adjust interest cost. This is the excess of rupee-loan interest over foreign-loan interest: 18,00,000 − 8,00,000 = ₹10,00,000, which is less than the ₹15,00,000 loss. Borrowing cost capitalised = 8,00,000 + 10,00,000 = ₹18,00,000. The remaining ₹5,00,000 of exchange loss is not borrowing cost. Capitalising the full loss would give the wrong figure of ₹23,00,000.
Did you get it right without looking?
One question tells you little. A timed set on AS 16 Borrowing Costs shows your real accuracy, how long you take and where you lose marks.
More AS 16 Borrowing Costs questions
- Godavari Pharma Ltd. is constructing a manufacturing plant that is a qualifying asset. Construction of the plant was completed and the asset…
- Vihaan Builders Ltd. has no specific borrowing for a plant under construction. During the year it had two general borrowings: Rs 40,00,000 a…
- Dhanush Realty Ltd took a specific term loan of Rs 5 crore at 9% p.a. on 1 April 2025 to construct a qualifying asset. Active development wa…
- Gupta Developers Ltd is constructing a residential complex of three towers with a specific loan. Tower A has been completed and is ready for…
- Lotus Realty Ltd is constructing a residential complex with two towers financed by a term loan. Tower A is complete and can be used independ…
- Nilgiri Power Ltd. is constructing a substation (qualifying asset) from 1 April 2025. It took a specific loan of Rs 1,00,00,000 at 8% p.a. o…