CA Intermediate · Advanced Accounting · AS 16 Borrowing Costs
Nilgiri Power Ltd. is constructing a substation (qualifying asset) from 1 April 2025. It took a specific loan of Rs 1,00,00,000 at 8% p.a. on 1 April 2025. Expenditure on the asset: Rs 60,00,000 on 1 April 2025 and Rs 90,00,000 on 1 October 2025. The balance of the specific loan stayed in a bank account earning no income. General borrowings of Rs 2,00,00,000 at 11% p.a. were outstanding all year. Asset not ready at 31 March 2026. What total borrowing cost is capitalised for 2025-26?
Under AS 16, the specific loan interest of Rs 8,00,000 is capitalised, and expenditure beyond that loan is funded by general borrowings at 11%. Rs 50,00,000 for six months adds Rs 2,75,000, so the total is Rs 10,75,000.
- ARs 10,25,000Correct
- BRs 11,00,000
- CRs 10,00,000
- DRs 8,00,000
Explanation
Specific loan interest = 1,00,00,000 x 8% = Rs 8,00,000 (fully capitalised). The expenditure beyond the specific loan: on 1 October, expenditure cumulative is 1,50,00,000 against the loan of 1,00,00,000, so excess is 50,00,000 funded from general borrowings. Interest = 50,00,000 x 11% x 6/12 = Rs 2,75,000. Total = 8,00,000 + 2,75,000 = Rs 10,75,000.
Did you get it right without looking?
One question tells you little. A timed set on AS 16 Borrowing Costs shows your real accuracy, how long you take and where you lose marks.
More AS 16 Borrowing Costs questions
- Anand Cement Ltd borrowed ₹60,00,000 at 10% p.a. on 1 April specifically to construct a storage terminal, a qualifying asset whose construct…
- Meena Textiles Ltd. began constructing a new factory on 1 April 2025 using a specific loan of ₹50,00,000 at 9% p.a. Active development was s…
- Kaveri Infra Ltd. is building a bridge, a qualifying asset. Expenditure was ₹60,00,000 on 1 April 2025 and ₹40,00,000 on 1 October 2025, fun…
- Nilgiri Power Ltd. is constructing a plant that is a qualifying asset. Part of the plant, Unit A, was completed and put to use on 1 January …
- Vindhya Cements Ltd. is building a plant, which is a qualifying asset. Construction started on 1 April 2025. Because of a labour dispute, ac…
- Dhanush Realty Ltd took a specific term loan of Rs 5 crore at 9% p.a. on 1 April 2025 to construct a qualifying asset. Active development wa…