CMA Final · Strategic Cost Management · Variance Analyses
Kaveri Engineering's standard labour cost is 4 hours per unit at Rs 150 per hour. For 2,000 units, 8,400 hours were paid at Rs 155 per hour, of which 400 hours were idle, with no idle time allowed in standards. What is the labour efficiency variance?
The labour efficiency variance is nil. Standard hours for 2,000 units are 8,000, and actual productive hours are 8,400 paid less 400 idle, which is 8,000. Idle time is reported separately as the idle time variance, not within efficiency.
- ARs 30,000 AdverseCorrect
- BRs 60,000 Adverse
- CRs 0
- DRs 30,000 Favourable
Explanation
Standard hours = 2,000 x 4 = 8,000. Actual hours worked = 8,400 - 400 = 8,000. Efficiency variance = (8,000 - 8,000) x 150 = nil. So the answer is Rs 0; the idle time of 400 hours x 150 = Rs 60,000 is a separate variance.
Did you get it right without looking?
One question tells you little. A timed set on Variance Analyses shows your real accuracy, how long you take and where you lose marks.
More Variance Analyses questions
- Mehta Components budgets fixed overheads of Rs 2,40,000 for 6,000 units (absorption rate Rs 40 per unit). Actual output was 5,500 units and …
- Lakshmi Plastics budgeted fixed overhead of Rs 6,00,000 for 20,000 units (standard 2 hours per unit; budgeted 40,000 hours). Actual output w…
- Rohan Chemicals uses a standard mix of 60 kg of A at Rs 20 per kg and 40 kg of B at Rs 30 per kg to yield 90 kg of output. Actual input for …
- Budgeted sales were 1,000 units at Rs 200 with standard cost Rs 140 per unit. Actual sales were 1,100 units at Rs 195. What is the sales mar…
- A firm sets standard variable overhead at Rs 8 per machine hour. For 3,000 units, standard is 2 machine hours per unit. Actual output was 3,…
- Aarav Plastics budgeted to produce 5,000 units of a moulded part using 2 kg of resin per unit at a standard price of Rs 80 per kg. Actual ou…