CA Intermediate · Advanced Accounting · AS 16 Borrowing Costs
Kaveri Infra Ltd. took a specific term loan of ₹2,00,00,000 at 10% p.a. on 1 April 2025 solely to construct a qualifying asset. Construction continued throughout the year ended 31 March 2026. Part of the loan was not yet spent and was temporarily invested, earning ₹3,50,000. What amount of borrowing cost should be capitalised for the year?
The amount to capitalise is ₹16,50,000. Interest on the specific loan is ₹20,00,000, and AS 16 requires the income earned from temporary investment of unspent specific borrowings, ₹3,50,000, to be deducted from the borrowing costs eligible for capitalisation.
- A₹20,00,000
- B₹16,50,000Correct
- C₹23,50,000
- D₹3,50,000
Explanation
Interest on the specific loan is ₹2,00,00,000 × 10% = ₹20,00,000. Income earned on temporary investment of the unspent specific borrowing is deducted: ₹20,00,000 − ₹3,50,000 = ₹16,50,000. Capitalising ₹20,00,000 ignores the income to be deducted.
Did you get it right without looking?
One question tells you little. A timed set on AS 16 Borrowing Costs shows your real accuracy, how long you take and where you lose marks.
More AS 16 Borrowing Costs questions
- Konark Engineering Ltd took a term loan of Rs 10,00,00,000 at 12% p.a. on 1 April 2025 solely to build a new plant. Physical construction wa…
- Malabar Shipyards Ltd. borrowed ₹1,00,00,000 at 12% p.a. on 1 April 2025 specifically to build an office complex. Construction started on 1 …
- Konkan Textiles Ltd. began constructing a new dyeing unit on 1 April 2025. It borrowed Rs 2,00,00,000 specifically for the project at 9% p.a…
- Ganga Power Ltd. is building a power unit, a qualifying asset, from 1 April 2025. A specific loan of Rs 40,00,000 at 11% p.a. was taken on 1…
- Vindhya Engineering Ltd. is building a plant (a qualifying asset) financed from its general borrowings. During the year, the expenditure on …
- Meenakshi Pharma Ltd. took a specific loan of Rs 1,20,00,000 at 10% p.a. on 1 April 2025 to build a plant. Its general borrowings were Rs 80…