Kaveri Plastics Ltd completed a corporate insolvency resolution process 18 months before the date it proposes to initiate a pre-pack. It is not currently in CIRP and no liquidation order has been passed. Under section 54A(2), what is the position on the three-year condition?
Kaveri Plastics fails the condition. Section 54A(2)(a) bars a debtor that has undergone a pre-pack or completed a CIRP in the three years before the initiation date. Completing CIRP 18 months ago falls inside that window, regardless of who started it or whether liquidation followed.
- AIt fails the condition, as it completed CIRP within the three years preceding the initiation dateCorrect
- BIt satisfies the condition, because only a prior pre-pack counts against eligibility
- CIt satisfies the condition, because the bar applies only if liquidation followed the CIRP
- DIt fails the condition only if the CIRP was started by an operational creditor
Explanation
Section 54A(2)(a) requires that the debtor has not undergone a pre-pack or completed a CIRP during the three years preceding the initiation date. Completion of CIRP 18 months earlier falls within that window, so the debtor is ineligible. The identity of the applicant in the earlier CIRP is irrelevant.
Did you get it right without looking?
One question tells you little. A timed set on Pre-Packaged Insolvency Resolution Process shows your real accuracy, how long you take and where you lose marks.
More Pre-Packaged Insolvency Resolution Process questions
- The resolution professional of Himalaya Foods Ltd files a termination application under Section 54D(3) on 10 July because no plan was approv…
- Sundaram Textiles Ltd's application for a pre-packaged insolvency resolution process (PPIRP) is admitted by the Adjudicating Authority. Whic…
- In Rudra Engineering Ltd's PPIRP, the Adjudicating Authority had earlier passed an order under section 54J(2). The RP now applies for termin…
- Sundaram Auto Components Pvt Ltd, an MSME, is in a pre-packaged insolvency resolution process (PPIRP) that commenced on 1 March. The committ…
- The pre-packaged insolvency commencement date for Bharat Components Ltd is 10 January. By 9 April (ninety days later) the committee of credi…
- A PPIRP of Narmada Polymers Ltd commenced on 10 April. No resolution plan was approved by the committee of creditors within 90 days of that …