CS Professional · Corporate Restructuring, Valuation and Insolvency · Pre-Packaged Insolvency Resolution Process
Kaveri Textiles Ltd completed a corporate insolvency resolution process 18 months before the proposed initiation date and now wishes to start a pre-pack. All other conditions are met. What is the position?
Kaveri Textiles cannot proceed. Section 54A(2)(a) requires that the debtor has not undergone a pre-pack or completed a CIRP in the three years before the initiation date, and 18 months is within that period. Creditor consent does not remove this bar.
- AIt can proceed, as the three-year bar applies only to liquidation
- BIt can proceed if two-thirds of financial creditors consent
- CIt cannot proceed, as it completed a CIRP within the three years preceding the initiation dateCorrect
- DIt can proceed if the Adjudicating Authority waives the bar
Explanation
Section 54A(2)(a) requires that the corporate debtor has not undergone a pre-pack or completed a CIRP during the three years preceding the initiation date. 18 months falls within that window, and creditor consent cannot override the condition.
Did you get it right without looking?
One question tells you little. A timed set on Pre-Packaged Insolvency Resolution Process shows your real accuracy, how long you take and where you lose marks.
More Pre-Packaged Insolvency Resolution Process questions
- Kaveri Components Pvt Ltd is admitted into PPIRP. The corporate debtor's application names Mr. Iyer as the proposed resolution professional,…
- The resolution professional of Kaveri Textiles Ltd files a termination application under Section 54D(3) after no plan was approved. Within h…
- Prakash Tools Pvt Ltd, an MSME, is in a pre-packaged insolvency resolution process (PIRP). The committee of creditors (CoC) has not approved…
- The Adjudicating Authority admits the pre-pack application of Bhoomi Agro Ltd. The application named an insolvency professional against whom…
- Sunrise Packaging Pvt Ltd, a company classified as a micro enterprise under the MSMED Act, 2006, has committed a default as defined in secti…
- During a PPIRP of Narmada Foods Pvt Ltd, before any plan is approved, the CoC votes to terminate the process and the RP informs the Adjudica…