ACCA Applied Skills · Performance Management · Standard costing
Kestrel Ltd budgeted to use 4,000 kg of material at a standard price of $5.00 per kg. It actually bought and used 4,200 kg at a cost of $20,160. What is the material price variance?
The material price variance is $840 favourable, because 4,200 kg should have cost $21,000 at standard but actually cost $20,160.
- A$840 adverse
- B$840 favourableCorrect
- C$960 adverse
- D$1,000 favourable
Explanation
Material price variance = (actual quantity x standard price) - actual cost. Actual quantity at standard price = 4,200 kg x $5.00 = $21,000. Actual cost = $20,160. Since the actual cost is lower than the standard cost of the quantity purchased, the variance is $21,000 - $20,160 = $840 favourable.
Did you get it right without looking?
One question tells you little. A timed set on Standard costing shows your real accuracy, how long you take and where you lose marks.
More Standard costing questions
- Zeta Co uses standard costing. The standard labour rate is $12 per hour. In May, 5,000 hours were paid at a total cost of $62,000. Of these,…
- Dale Co has a standard labour rate of $8 per hour. Last month 3,000 hours were paid for and 2,760 hours were worked. What is the idle time v…
- Marlow Co budgeted sales of 10,000 units at a standard contribution of $8 per unit. The market contracted, and the ex-post achievable market…
- Which of the following is the most likely cause of an adverse material price variance combined with a favourable material usage variance?
- A manager is held responsible for a material usage variance that arose largely because a purchasing decision led to substandard material bei…
- Brook Ltd budgets 1 standard hour per unit at $15 per hour. In June it produced 2,000 units using 2,100 hours worked; 2,250 hours were paid,…