Dale Co has a standard labour rate of $8 per hour. Last month 3,000 hours were paid for and 2,760 hours were worked. What is the idle time variance?
The idle time variance is $1,920 adverse. There were 240 hours paid but not worked (3,000 less 2,760), valued at the standard rate of $8 per hour. Because the company paid for time that produced nothing, the variance is always adverse.
- A$1,920 adverseCorrect
- B$2,400 adverse
- C$1,920 favourable
- D$22,080 adverse
Explanation
Idle hours = 3,000 - 2,760 = 240. At the standard rate of $8 this is $1,920. Idle time always represents paid but unproductive time, so it is adverse. $2,400 wrongly uses a different base of 300 hours.
Did you get it right without looking?
One question tells you little. A timed set on Standard costing shows your real accuracy, how long you take and where you lose marks.
More Standard costing questions
- Which of the following is the most likely cause of an adverse material price variance combined with a favourable material usage variance?
- A company reports an adverse labour efficiency variance together with a favourable labour rate variance. Which explanation is most consisten…
- A manager is held responsible for a material usage variance that arose largely because a purchasing decision led to substandard material bei…
- Zeta Co uses standard costing. The standard labour rate is $12 per hour. In May, 5,000 hours were paid at a total cost of $62,000. Of these,…
- Brook Ltd budgets 1 standard hour per unit at $15 per hour. In June it produced 2,000 units using 2,100 hours worked; 2,250 hours were paid,…
- Orion Co makes one product with a standard of 4 labour hours at $10 per hour. Actual output was 1,500 units. Hours paid were 6,400 at $10.50…