Kestrel Ltd makes three products using a single machine that is the only bottleneck. Product X sells for $50 with material cost $20 and uses 2 machine hours. Product Y sells for $60 with material cost $30 and uses 1.5 machine hours. Product Z sells for $40 with material cost $10 and uses 3 machine hours. Which product should Kestrel give first priority when allocating bottleneck hours?
Product Y should have priority because it earns the highest throughput per bottleneck hour. Throughput is selling price less material cost, giving $30 for each product, but Y uses only 1.5 hours, so it earns $20 per hour, compared with $15 for X and $10 for Z.
- AProduct X, with a return of $15 per machine hour
- BProduct Y, with a return of $20 per machine hourCorrect
- CProduct Z, with a return of $10 per machine hour
- DProduct Z, because it has the highest throughput of $30 per unit
Explanation
Throughput per unit is price less material: X $30, Y $30, Z $30. Return per bottleneck hour: X 30/2 = $15, Y 30/1.5 = $20, Z 30/3 = $10. Y ranks first. Choosing Z because of unit throughput ignores the bottleneck usage.
Did you get it right without looking?
One question tells you little. A timed set on Performance improvement models and techniques shows your real accuracy, how long you take and where you lose marks.
More Performance improvement models and techniques questions
- Kestrel Logistics wants to improve its warehouse order-picking process. The board decides to study the order-picking methods of an online fa…
- Harbin Foods applies the Theory of Constraints. Management has identified the bottleneck as its packing line and has ensured it is never idl…
- Dalton Hospital Group has a single performance target of reducing patient waiting times. Staff begin to move patients between queues and rec…
- Marlow Co has a throughput accounting ratio (TPAR) calculation for its main product. Throughput per factory hour is $45 and total factory co…
- Ostrava Metals is introducing a just-in-time (JIT) system as part of a lean programme. Which outcome is most consistent with successful JIT …
- Kestrel Components is considering a BPR project. Which of the following is the most likely cause of the project failing to deliver its expec…