Malwa Constructions Ltd. has a contract for Rs 90 lakh. Up to the reporting date, costs incurred are Rs 54 lakh, which include Rs 6 lakh of materials purchased and delivered to site but not yet used. Estimated total cost is Rs 100 lakh including these materials. Using the cost proportion method, what is the stage of completion?
The stage of completion is 48 percent. Materials delivered to site but not yet used are excluded from costs incurred when measuring progress, so Rs 48 lakh is divided by estimated total cost of Rs 100 lakh.
- A48%Correct
- B54%
- C60%
- D90%
Explanation
Under AS 7, costs of materials not yet used in the contract are excluded when computing stage of completion. Costs counted = 54-6 = 48 lakh. Stage = 48/100 = 48%. Using 54% wrongly includes unused materials.
Did you get it right without looking?
One question tells you little. A timed set on AS 7 Construction Contracts shows your real accuracy, how long you take and where you lose marks.
More AS 7 Construction Contracts questions
- Konark Infra Ltd. is building a flyover for a state government under a fixed price contract of Rs 80 lakh. At the year-end, costs incurred t…
- Tulsi Projects Ltd has a fixed price contract of ₹120 lakh. At the end of year 1, costs incurred were ₹30 lakh, including ₹6 lakh of materia…
- Ganga Builders Ltd has a fixed-price contract of ₹50 lakh. At the year end, costs incurred are ₹30 lakh, all relating to work done, and esti…
- Malwa Constructions Ltd. has a fixed price contract of Rs 500 lakh. At the end of year 1, cost incurred is Rs 360 lakh and estimated cost to…
- Gujarat Civil Works Ltd is executing a contract where, because of a legal dispute over the contract's enforceability, the outcome cannot be …
- Deccan Builders Ltd. has a fixed price contract for Rs 200 lakh. Cost incurred to date is Rs 120 lakh, which includes Rs 20 lakh of steel pu…