ACCA Applied Knowledge · Management Accounting · Nature and purpose of budgeting
Marlow Co sets budgets using a participative approach. Which of the following is a potential disadvantage of participation in budget setting?
A potential disadvantage of participative budgeting is that managers may build budgetary slack into the budget, by overstating costs or understating revenues, to make targets easier to meet. Participation normally improves commitment and uses local knowledge, so the other options are not disadvantages of participation.
- AManagers feel less committed to the targets
- BBudgetary slack may be built into the budgetCorrect
- CSenior management's knowledge is not used
- DLocal knowledge of operating conditions is ignored
Explanation
When managers help set their own budgets, they may pad costs or understate revenues to make targets easier to achieve, creating slack. Participation usually raises motivation and commitment and uses local knowledge, so the other options describe advantages or benefits of participation that are the reverse of what is stated.
Did you get it right without looking?
One question tells you little. A timed set on Nature and purpose of budgeting shows your real accuracy, how long you take and where you lose marks.
More Nature and purpose of budgeting questions
- Bexley Co has a budget committee that sets a tight sales target of 50,000 units for the year. Management states that the budget will be used…
- A company plans to sell 12,000 units next period. Opening finished goods inventory is 1,500 units and the company wants closing inventory of…
- Budgeted sales for a product are 8,000 units. Opening inventory of finished goods is 1,500 units and the company wants closing inventory to …
- Kestrel Ltd uses a rolling budget. It prepares a 12-month budget and, at the end of each quarter, drops the quarter just completed and adds …
- Which of the following is the correct order in which a typical manufacturing company would prepare its budgets when sales demand is the prin…
- Which of the following budgets would normally be prepared FIRST in a company whose principal budget factor is sales demand?