The sales director of Harlow Co wants to raise the sales budget by 20% to inspire the sales team, even though the production manager says capacity cannot support it. Which budgeting purpose is MOST at risk of failing as a result?

Coordination is most at risk. A sales budget that exceeds production capacity means the departmental plans do not fit together, so the budgets are inconsistent. The budget should be built around the principal budget factor, here capacity, so that all departments work to compatible plans.

  1. ACoordination of the activities of different departmentsCorrect
  2. BCommunication of the budget to junior staff
  3. CProvision of a basis for variance reporting
  4. DAuthorisation of expenditure by senior managers

Explanation

A sales budget that production cannot meet means departmental plans are not aligned, so coordination fails. The principal budget factor, here capacity, should drive the other budgets. Variance reporting and authorisation can still operate, though the variances would be large and unhelpful.