ACCA Applied Knowledge · Management Accounting · Variance calculations and analysis
Marlow Ltd budgeted to produce 4,000 units in the period, with budgeted fixed overheads of $60,000. Actual production was 4,300 units. Actual fixed overheads were $61,000. Using absorption costing with the rate per unit, what is the total fixed overhead volume variance?
The fixed overhead volume variance is $4,500 favourable. The absorption rate is $15 per unit, so 4,300 units absorb $64,500, which is $4,500 more than the $60,000 budget. Producing more than budgeted over-absorbs fixed overhead, giving a favourable variance.
- A$4,500 favourableCorrect
- B$4,500 adverse
- C$1,000 adverse
- D$5,500 favourable
Explanation
Absorption rate = $60,000/4,000 = $15 per unit. Absorbed = 4,300 x $15 = $64,500. Budgeted fixed overhead is $60,000, so the volume variance is $64,500 - $60,000 = $4,500 favourable. The $5,500 figure wrongly compares absorbed with actual cost, giving the total under-/over-absorption.
Did you get it right without looking?
One question tells you little. A timed set on Variance calculations and analysis shows your real accuracy, how long you take and where you lose marks.
More Variance calculations and analysis questions
- Brenner Co's standard is 5 kg of material at $12 per kg per unit. Actual output was 3,000 units. Actual material used was 15,400 kg at an ac…
- Fenwick Co uses a standard of 2 hours per unit at $9 per hour. Actual output was 2,500 units. Actual hours paid were 5,200, of which 200 wer…
- Zeta Ltd uses standard marginal costing. Budgeted sales were 2,000 units and actual sales were 2,150 units. The standard contribution is $12…
- A company's sales price variance for a period is adverse and its sales volume variance is favourable. Which of the following is the most lik…
- Brindle Co has a standard labour rate of $9 per hour. In June, 3,200 hours were paid at an actual cost of $30,080, of which 150 hours were r…
- Kestrel Ltd budgeted fixed production overheads of $60,000 for the period, based on 12,000 units at 2 labour hours per unit. Actual fixed ov…