Maximise Z = 4x + 6y subject to 2x + 3y <= 12, x <= 5, x, y >= 0. Which statement is correct?
The problem has multiple optimal solutions with maximum Z of 24. The objective function is exactly twice the left side of the constraint 2x+3y<=12, so the iso-profit line coincides with that constraint edge. Every point on the edge from (0,4) to (5, 2/3) yields the same Z of 24.
- AUnique optimum at (5, 0) with Z = 20
- BUnique optimum at (0, 4) with Z = 24
- CMultiple optimal solutions; maximum Z = 24 attained along the segment from (0, 4) to (5, 2/3)Correct
- DNo feasible solution exists
Explanation
The objective 4x+6y is 2 times (2x+3y), so the iso-profit line is parallel to the constraint 2x+3y=12. Every point on that line within the region gives Z = 24. Corner points (0,4) and (5, 2/3) both give 24: 4*5+6*(2/3)=20+4=24. Choosing a single point such as (0,4) as unique ignores the parallel line.
Did you get it right without looking?
One question tells you little. A timed set on Optimum Allocation of Resources - LPP shows your real accuracy, how long you take and where you lose marks.
More Optimum Allocation of Resources - LPP questions
- In a simplex iteration, x1 is the entering variable. Its column coefficients in three constraint rows are 4, 5 and −3, with corresponding RH…
- A graphical LPP has constraints x + y <= 6 and x + y >= 10 with x, y >= 0. The correct conclusion is that the problem:
- In a maximisation simplex table, the Cj − Zj row reads: x1 = 5, x2 = 8, s1 = 0, s2 = −2. Which variable should enter the basis and is the so…
- A firm maximises Z = 40x + 30y subject to x + y <= 8, x <= 5, and x, y >= 0. What is the maximum value of Z (in rupees)?
- A firm maximises Z = 5x + 4y subject to x + y <= 10, x <= 6, and x, y >= 0. What is the optimal value of Z?
- Sharma Furnitures makes tables (x) and chairs (y). A table needs 4 hours of carpentry and a chair needs 2 hours; 240 carpentry hours are ava…