Sharma Furnitures makes tables (x) and chairs (y). A table needs 4 hours of carpentry and a chair needs 2 hours; 240 carpentry hours are available per week. Which constraint correctly represents this?
The constraint is 4x + 2y <= 240. Each table consumes 4 carpentry hours and each chair 2 hours, so total usage is 4x + 2y, and this cannot exceed the 240 hours available. Reversing the coefficients or the inequality sign would misstate the resource limit.
- A4x + 2y >= 240
- B2x + 4y <= 240
- C4x + 2y <= 240Correct
- D4x + 2y = 240 is the only permissible form and x,y can be negative
Explanation
Hours used = 4 per table times x plus 2 per chair times y = 4x + 2y. Availability is a maximum, so the sign is less than or equal. Option 2 swaps the coefficients, and option 1 reverses the inequality.
Did you get it right without looking?
One question tells you little. A timed set on Optimum Allocation of Resources - LPP shows your real accuracy, how long you take and where you lose marks.
More Optimum Allocation of Resources - LPP questions
- Which of the following is a basic assumption of linear programming?
- A company must produce at least 60 units in total of products A and B (x + y >= 60), and at most 40 units of A (x <= 40). Cost is minimised:…
- In converting a maximisation LPP with all constraints of the '≤' type into the standard form for the simplex method, what is added to each c…
- A firm maximises profit subject to the constraints x + y <= 4 and x + y >= 9, with x, y >= 0. What does the graphical method show?
- In the graphical method of solving a two-variable linear programming problem, the set of all points that satisfy every constraint, including…
- Sundaram Metals maximises profit Z = 5x + 4y subject to: 6x + 4y ≤ 24 (machine hours) and x + 2y ≤ 6 (labour hours), x, y ≥ 0. The optimal s…