Meenakshi Labs has a quality inspection pool of ₹3,60,000. The practical capacity is 1,200 inspections, but only 900 were performed in the year. If ABC rates are set on practical capacity, what amount of inspection cost is the cost of unused capacity and not assigned to products?
The unused-capacity cost is ₹90,000. The inspection rate at practical capacity is ₹300 (₹3,60,000 ÷ 1,200), so the 900 inspections performed absorb ₹2,70,000. The remaining 300 inspections of idle capacity at ₹300 each amount to ₹90,000, which is not charged to products.
- A₹90,000Correct
- B₹1,20,000
- C₹2,70,000
- D₹60,000
Explanation
The rate on practical capacity is ₹3,60,000 ÷ 1,200 = ₹300 per inspection. Products absorb 900 × 300 = ₹2,70,000. The balance, 300 unused inspections × ₹300 = ₹90,000, is the cost of unused capacity. ₹2,70,000 is the amount assigned to products, not the unused part.
Did you get it right without looking?
One question tells you little. A timed set on Activity Based Costing shows your real accuracy, how long you take and where you lose marks.
More Activity Based Costing questions
- Nilgiri Tools has overheads of ₹6,00,000 absorbed on a per-unit basis under traditional costing. It makes 9,000 units of a high-volume produ…
- Which of the following correctly lists the usual sequence of steps when implementing Activity Based Costing?
- In Activity Based Costing, an activity that is performed once for every batch of products produced, irrespective of the number of units in t…
- Kaveri Industries has overheads of ₹6,00,000, split equally between a setup pool (₹3,00,000) and an inspection pool (₹3,00,000). Setups tota…
- Product P: 5,000 units, direct material ₹120 per unit, direct labour ₹60 per unit. Ordering cost pool is ₹1,50,000 for 300 purchase orders i…
- Nalanda Electronics has two cost pools: machine setups ₹3,00,000 (driver: number of setups) and material handling ₹2,40,000 (driver: number …