CMA Intermediate · Management Accounting · Activity Based Costing
Nilgiri Tools has overheads of ₹6,00,000 absorbed on a per-unit basis under traditional costing. It makes 9,000 units of a high-volume product and 1,000 units of a low-volume, complex product. Analysis shows the low-volume product consumes 50% of all activity drivers. Per unit, traditional costing compared with ABC for the low-volume product:
Traditional costing undercosts the low-volume product by ₹240 per unit. It charges ₹60 per unit (₹6,00,000 over 10,000 units), while ABC traces half the overhead, ₹3,00,000, to the 1,000 units, or ₹300 each. The high-volume product is overcosted to compensate.
- AUndercosts it by ₹240Correct
- BOvercosts it by ₹240
- CUndercosts it by ₹300
- DUndercosts it by ₹60
Explanation
Traditional rate = ₹6,00,000/10,000 = ₹60 per unit. ABC assigns 50% = ₹3,00,000 to the low-volume product, which is ₹300 per unit over 1,000 units. Difference = 300 − 60 = ₹240 undercosted. The high-volume product is correspondingly overcosted, which is cross-subsidisation.
Did you get it right without looking?
One question tells you little. A timed set on Activity Based Costing shows your real accuracy, how long you take and where you lose marks.
More Activity Based Costing questions
- Rao Auto Parts uses ABC with a machine-setup pool of ₹6,00,000 driven by 400 setups. Under ABM, it plans to cut setups by 25% through a proc…
- Vihar Foods Ltd uses ABC. Total overhead of ₹6,00,000 is made of ordering ₹2,40,000 (driver: 800 purchase orders) and quality control ₹3,60,…
- Gupta Textiles has a materials handling activity costing ₹5,40,000 for the year. The activity is used for 9,000 movements in the year, where…
- Sundaram Pumps Ltd has a setup cost pool of ₹2,40,000 for the year, and the cost driver is the number of machine setups. A total of 80 setup…
- Bharat Tools Ltd makes two products, X and Y. Total overheads are ₹4,20,000. Under the traditional method, overheads are absorbed on direct …
- Neha Appliances has a total overhead of ₹10,00,000. Under the traditional method, it is absorbed on direct labour hours (50,000 hours), and …