CMA Final · Strategic Financial Management · Evaluation of Risky Proposals for Investment Decisions
Meenakshi Textiles is evaluating a project whose cash flows are uncertain. Its normal required return is 12% and the project is judged under the certainty equivalent approach. Year 1 expected cash flow is Rs 5,00,000 with a certainty equivalent coefficient of 0.80. The risk-free rate is 8%. Initial outlay is Rs 3,50,000 and the project lasts one year only. What is the NPV using the certainty equivalent method?
Under the certainty equivalent method the cash flow is first scaled by the coefficient to Rs 4,00,000 and then discounted at the risk-free rate of 8%, giving Rs 3,70,370. Subtracting the outlay of Rs 3,50,000 gives an NPV of about Rs 20,370.
- ARs 7,143
- BRs 20,370 (approximately)Correct
- CRs 57,143
- DRs 1,50,000
Explanation
Certainty equivalent cash flow = 5,00,000 x 0.80 = 4,00,000. It is discounted at the risk-free rate of 8%: 4,00,000/1.08 = 3,70,370. NPV = 3,70,370 - 3,50,000 = 20,370. Discounting at 12% gives 3,57,143, NPV 7,143, which is the wrong rate.
Did you get it right without looking?
One question tells you little. A timed set on Evaluation of Risky Proposals for Investment Decisions shows your real accuracy, how long you take and where you lose marks.
More Evaluation of Risky Proposals for Investment Decisions questions
- Ganga Polymers is considering a project with an initial cost of Rs 6,00,000 and an annual cash inflow of Rs 2,40,000 for 4 years. Using a ri…
- Shree Plastics has a project with initial outlay Rs 1,00,000 and cash flows in year 1 and year 2 as follows. Year 1: Rs 60,000 (probability …
- A project has an initial outlay of Rs 5,00,000 and yields annual cash inflows of Rs 1,50,000 for 5 years. Cost of capital is 10% and the 5-y…
- Meera Plastics is assessing a project with an initial outlay of ₹10,00,000 and a uniform annual inflow of ₹3,50,000. The present value annui…
- A project of Kaveri Engineering has an initial outlay of Rs 1,00,000 and a single cash inflow at the end of year 1 with the following probab…
- For a project, the expected NPV is Rs 40,000 and the standard deviation of NPV is Rs 20,000. Assuming NPV is normally distributed, what is t…