CMA Final · Strategic Financial Management · Evaluation of Risky Proposals for Investment Decisions
For a project, the expected NPV is Rs 40,000 and the standard deviation of NPV is Rs 20,000. Assuming NPV is normally distributed, what is the approximate probability that the project's NPV is negative? (Area from mean to Z = 2 is 0.4772.)
The probability of a negative NPV is about 2.28%. The cutoff of zero lies two standard deviations below the mean of 40,000, since the standard deviation is 20,000. The one-sided tail beyond Z of 2 is 0.5 minus 0.4772, which equals 0.0228.
- A4.56%
- B2.28%Correct
- C47.72%
- D5.00%
Explanation
Z = (0 - 40,000)/20,000 = -2. Area from the mean to Z=2 is 0.4772, so the tail beyond is 0.5 - 0.4772 = 0.0228. The probability of a negative NPV is 2.28%. The 4.56% option wrongly doubles the tail by using both sides.
Did you get it right without looking?
One question tells you little. A timed set on Evaluation of Risky Proposals for Investment Decisions shows your real accuracy, how long you take and where you lose marks.
More Evaluation of Risky Proposals for Investment Decisions questions
- A project of Kaveri Industries has an initial outlay of Rs 2,00,000 and a single inflow after one year. The inflow is Rs 1,00,000 with proba…
- A project of Arjun Auto has a base-case NPV of Rs 12 lakh. The present value of annual sales-linked inflows is Rs 80 lakh. Management wants …
- Himalaya Power Ltd uses a risk-adjusted discount rate derived from CAPM. The risk-free rate is 8%, the expected market return is 14%, and th…
- Aarav Ltd uses a risk-adjusted discount rate. The risk-free rate is 8%, and the project is assigned a risk premium of 6%. The project requir…
- A project of Sundaram Textiles has a certainty-equivalent approach applied. Expected cash flow in Year 1 is ₹2,00,000 with a certainty-equiv…
- Meera Auto Ltd invests Rs 10 lakh in a project with a two-year life. Expected net cash inflows are Rs 6 lakh in Year 1 and Rs 8 lakh in Year…