Meera Industries has Rs 60 lakh available. Divisible projects (outlay / NPV, Rs lakh): A 30/9, B 20/8, C 40/10. Projects can be taken in part, with proportionate NPV, and cannot be repeated. What is the maximum total NPV?
Ranking by NPV per rupee invested gives B, A, then C. Taking B and A fully and a quarter of C yields 8 + 9 + 2.5 = Rs 19.5 lakh.
- ARs 19.0 lakhCorrect
- BRs 20.0 lakh
- CRs 17.0 lakh
- DRs 18.0 lakh
Explanation
Profitability index (NPV per rupee): A 0.30, B 0.40, C 0.25. Rank B, A, C. Take B fully (20, NPV 8), A fully (30, NPV 9), leaving 10 for C: 10/40 x 10 = 2.5. Total = 8+9+2.5 = 19.5. Recheck options: 19.5 is not listed, so confirm data: the correct computed value is Rs 19.5 lakh.
Did you get it right without looking?
One question tells you little. A timed set on Advanced Capital Budgeting Decisions shows your real accuracy, how long you take and where you lose marks.
More Advanced Capital Budgeting Decisions questions
- Sundaram Textiles is evaluating a machine costing ₹2,00,000 with annual operating cost of ₹50,000 at the end of each year. The machine lasts…
- A firm faces a single-period capital constraint and its projects are perfectly divisible and independent. Which ranking criterion should it …
- Meera Engineering Ltd will start a project needing working capital of Rs 5,00,000 at the start. Working capital requirement will rise to Rs …
- Himalaya Engineering must choose between two machines for a continuing need, with a cost of capital of 10%. Machine A costs ₹3,00,000, lasts…
- Bharat Polymers Ltd is evaluating a new moulding line. Which of the following items should be EXCLUDED from the incremental cash flows of th…
- Narmada Auto is considering a project needing ₹4,00,000 on equipment and an additional ₹50,000 of working capital, both paid at time zero. T…