Meera Industries has Rs 60 lakh available. Divisible projects (outlay / NPV, Rs lakh): A 30/9, B 20/8, C 40/10. Projects can be taken in part, with proportionate NPV, and cannot be repeated. What is the maximum total NPV?

The maximum total NPV is Rs 19.5 lakh, from B fully, A fully and one-quarter of C.

  1. ARs 19.5 lakhCorrect
  2. BRs 20.0 lakh
  3. CRs 17.0 lakh
  4. DRs 18.0 lakh

Explanation

Since projects are divisible, rank them by NPV per rupee of outlay (profitability): A = 9/30 = 0.30, B = 8/20 = 0.40, C = 10/40 = 0.25. Ranking: B, A, C. Take B fully (outlay 20, NPV 8), then A fully (outlay 30, NPV 9), leaving Rs 10 lakh for C: 10/40 x 10 = 2.5. Total NPV = 8 + 9 + 2.5 = Rs 19.5 lakh.