CMA Intermediate · Cost Accounting · Direct Expenses
Mehta Fabricators paid Rs 60,000 as hire of a special mould used only for Batch B (500 units), Rs 25,000 for a subcontracted plating job on the batch, and Rs 10,000 for factory insurance (general). Direct materials Rs 1,50,000 and direct wages Rs 90,000. Primes cost per unit of Batch B, treating all direct items (materials, wages, direct expenses), is:
Prime cost per unit is Rs 650. Direct expenses are mould hire 60,000 plus subcontract plating 25,000; adding materials 1,50,000 and wages 90,000 gives 3,25,000, divided by 500 units. General factory insurance is overhead and is excluded.
- ARs 650Correct
- BRs 530
- CRs 670
- DRs 610
Explanation
Direct expenses = 60,000 + 25,000 = 85,000; factory insurance is overhead. Prime cost = 1,50,000 + 90,000 + 85,000 = 3,25,000. Per unit = 3,25,000/500 = Rs 650. Including insurance gives 670.
Did you get it right without looking?
One question tells you little. A timed set on Direct Expenses shows your real accuracy, how long you take and where you lose marks.
More Direct Expenses questions
- Sharma Fabricators incurred the following for Job 52: royalty on the patented design Rs 18,000 (Rs 6 per unit on 3,000 units produced), spec…
- In a cost sheet prepared under CAS 10 (Direct Expenses), which of the following items would be treated as a direct expense of a specific job…
- Sharma Engineering pays a royalty of Rs 8 per unit produced to a patent holder for a patented process. In a month, 5,000 units were produced…
- A firm's cost sheet shows royalty on sales at Rs 4 per unit sold and royalty on production at Rs 3 per unit produced. Production was 10,000 …
- Ganga Tools Ltd hired a special machine for a single job, JOB-17, at Rs 6,000 per week for 4 weeks. The hire is traceable only to this job. …
- Verma Industries produced 8,000 units. Royalty is Rs. 6 per unit sold; 7,200 units were sold. Subcontracted job-specific processing cost was…