CA Intermediate · Cost and Management Accounting · Employee Cost and Direct Expenses
Mehta Fabricators pays piece wages under the Halsey premium plan. Standard time for a job is 40 hours, and the worker completes it in 30 hours. The hourly rate is Rs. 60 and the bonus share is 50% of time saved. What is the total earning for the job?
Total earning is Rs. 2,100. The worker is paid for 30 hours at Rs. 60, which is Rs. 1,800, plus a bonus of 50% of the 10 hours saved at Rs. 60, which is Rs. 300. The two amounts add up to Rs. 2,100.
- ARs. 1,800
- BRs. 2,100Correct
- CRs. 2,400
- DRs. 1,950
Explanation
Time saved = 40 - 30 = 10 hours. Time wages = 30 x 60 = Rs. 1,800. Bonus = 50% x 10 x 60 = Rs. 300. Total = Rs. 2,100. Rs. 1,800 omits the bonus, and Rs. 2,400 pays the full standard time, ignoring the 50% share.
Did you get it right without looking?
One question tells you little. A timed set on Employee Cost and Direct Expenses shows your real accuracy, how long you take and where you lose marks.
More Employee Cost and Direct Expenses questions
- Kapoor Fabrics has a skilled workman who produces 120 units in a 50-hour week. The standard output is 2 units per hour. He is paid under the…
- Which of the following is treated as an employee cost that is NOT directly traceable to a specific cost unit, and is therefore normally clas…
- Which of the following is a method of wage payment in which a worker's earnings are guaranteed at a minimum time-rate, with a bonus paid onl…
- Which of the following is treated as an indirect employee cost in a manufacturing company and therefore included in factory overheads?
- Under the Rowan plan, a worker has a time rate of Rs 30 per hour, standard time of 60 hours and actual time taken of 45 hours. What is the t…
- Which of the following is a direct expense chargeable to a specific job, rather than an overhead, in the books of a cost accountant at Iyer …