CA Intermediate · Cost and Management Accounting · Employee Cost and Direct Expenses
Which of the following is a method of wage payment in which a worker's earnings are guaranteed at a minimum time-rate, with a bonus paid only if the time taken is less than the standard time allowed, and the bonus equals a fixed percentage of time saved at the hourly rate?
The Halsey premium plan is the method described. Earnings are guaranteed at time rate, and if the job is finished faster than standard, the worker receives a fixed percentage of the time saved, valued at the hourly rate, as bonus. Rowan and Taylor use different bonus formulas.
- AHalsey premium planCorrect
- BRowan plan
- CTaylor's differential piece rate
- DStraight piece rate with guaranteed minimum
Explanation
In Halsey premium plan, bonus is a fixed percentage (commonly 50%) of the time saved multiplied by the hourly rate, over and above time wages. Rowan plan pays bonus as time saved/time allowed times time taken times rate, not a fixed percentage of time saved. Taylor's plan uses two piece rates depending on efficiency, not time saved.
Did you get it right without looking?
One question tells you little. A timed set on Employee Cost and Direct Expenses shows your real accuracy, how long you take and where you lose marks.
More Employee Cost and Direct Expenses questions
- Mehta Textiles employs 400 workers on average during the year. During the year 28 workers left and 12 were replaced; in addition 20 new work…
- Under the Rowan plan, a worker at Sundaram Engineering has a time allowed of 20 hours, takes 15 hours, and earns Rs 60 per hour. What is the…
- Under the Halsey premium plan, a worker at Pune Tools is paid Rs 50 per hour. The time allowed for a job is 40 hours and the worker complete…
- In a factory, the cost of idle time arising from a normal power failure of 2 hours per month is treated in cost accounting as follows:
- In a factory, the wages paid to workers for the time they were idle because of a power failure that lasted two hours are best treated in cos…
- Under Rowan plan, a worker at Sahyadri Metals has a standard time of 20 hours, a rate of Rs 60 per hour and takes 15 hours for a job. Total …