ACCA Strategic Professional · Strategic Business Reporting (International) · Provisions, contingencies and events after the reporting period

On 15 December 20X5, the board of Kappa Co decided to close a division and approved a detailed formal plan. Before the reporting date of 31 December 20X5, the plan was not announced and no employees or customers had been told. The closure would cost $4m in redundancy. Under IAS 37, how should Kappa treat the closure at 31 December 20X5?

No provision should be recognised. A restructuring provision requires a detailed formal plan and a valid expectation in those affected, created by starting implementation or announcing its main features. A board decision that has not been communicated creates no constructive obligation at the reporting date.

  1. ARecognise a $4m restructuring provision because the board approved a detailed formal plan
  2. BRecognise no provision because no valid expectation of closure has been raised in those affectedCorrect
  3. CDisclose a contingent liability only, with no provision, because the cost is uncertain
  4. DRecognise a provision for half of the $4m because the plan was approved in the last half of the month

Explanation

A restructuring constructive obligation arises only when there is a detailed formal plan and the entity has raised a valid expectation in those affected by starting implementation or announcing the main features. A private board decision is not enough, so no provision exists at the reporting date. Option 0 ignores the announcement requirement.

Did you get it right without looking?

One question tells you little. A timed set on Provisions, contingencies and events after the reporting period shows your real accuracy, how long you take and where you lose marks.

More Provisions, contingencies and events after the reporting period questions