ACCA Applied Knowledge · Management Accounting · Cost reductions and value enhancement
Orion Co uses kaizen costing. A product's cost in month 1 is $200 per unit. Kaizen targets require a 2% reduction in the previous month's cost each month, compounding. What is the target cost per unit in month 3 to the nearest cent?
The month 3 target cost is $192.08 per unit. A 2% compounding monthly reduction gives $196.00 in month 2 and $192.08 in month 3 from the month 1 cost of $200. Simple reductions would wrongly give $192.00.
- A$192.08Correct
- B$192.00
- C$196.00
- D$188.24
Explanation
Month 2 target = 200 x 0.98 = $196.00. Month 3 = 196 x 0.98 = $192.08. The $192.00 option uses a simple 2% of original cost per month over two months (4%), ignoring compounding. The $196.00 is only month 2, and $188.24 applies three reductions.
Did you get it right without looking?
One question tells you little. A timed set on Cost reductions and value enhancement shows your real accuracy, how long you take and where you lose marks.
More Cost reductions and value enhancement questions
- A product has a current cost of $50 per unit. A Kaizen programme requires a 2% reduction in the previous month's cost each month, starting w…
- Which of the following is a typical feature of target costing, as opposed to Kaizen costing?
- Which of the following is a typical step or feature of value engineering rather than a limitation of it?
- Which statement about value engineering is correct?
- Dunmore Co uses target costing for a product with a target selling price of $50 and a required margin of 30% on selling price. Variable cost…
- A company is value engineering a product. Current unit cost is $80 and the target cost for a required margin is $68. Redesign of components …