Orla plc is choosing between two projects. Project A gives a profit of $50,000 with probability 0.6 or $10,000 with probability 0.4. Project B gives a profit of $35,000 with certainty. The manager is risk-averse. Which statement is correct?

Project B is preferred. Project A has an expected value of $34,000, below Project B's certain $35,000. Since Project B also carries no variability, a risk-averse manager would choose it on both return and risk grounds.

  1. AProject A should be chosen because its expected value is $34,000 and it has a higher possible profit
  2. BProject B should be chosen on expected value because it exceeds Project A
  3. CProject A should be chosen because EV ignores risk and a risk-averse manager prefers variability
  4. DThe EVs are $34,000 and $35,000, so a risk-averse manager would prefer Project BCorrect

Explanation

EV of A = 50,000 x 0.6 + 10,000 x 0.4 = 30,000 + 4,000 = $34,000. B is $35,000 with no variability. B has the higher EV and no risk, so a risk-averse manager would choose B.