CA Intermediate · Advanced Accounting · AS 7 Construction Contracts
Rajdhani Constructions Ltd has a fixed-price contract of ₹80 lakh. At the end of Year 1, costs incurred were ₹20 lakh and estimated further costs to complete were ₹30 lakh. At the end of Year 2, cumulative costs incurred were ₹45 lakh and estimated further costs to complete were ₹15 lakh. The company uses the proportion of cost incurred to total estimated cost as the stage of completion, and all costs incurred reflect work performed. What contract revenue should be recognised for Year 2?
Year 2 revenue is ₹28 lakh. Cumulative completion at the end of Year 2 is 45/60, which is 75%, giving cumulative revenue of ₹60 lakh. Deducting the ₹32 lakh recognised in Year 1 leaves ₹28 lakh for Year 2.
- A₹60 lakh
- B₹32 lakh
- C₹25 lakh
- D₹28 lakhCorrect
Explanation
Year 1: total cost is 50, so completion is 40% and revenue is 32 lakh. Year 2: total cost is 45+15=60, so completion is 75% and cumulative revenue is 60 lakh. Year 2 revenue is 60-32=28 lakh. Recognising ₹60 lakh is wrong because it is the cumulative figure and ignores the revenue already recognised in Year 1.
Did you get it right without looking?
One question tells you little. A timed set on AS 7 Construction Contracts shows your real accuracy, how long you take and where you lose marks.
More AS 7 Construction Contracts questions
- Meridian Infra Ltd is building a flyover for a state government under a construction contract. Its accountant is listing the costs for the c…
- Gujarat Civil Works Ltd is executing a contract where, because of a legal dispute over the contract's enforceability, the outcome cannot be …
- Deccan Builders Ltd. has a fixed price contract for Rs 200 lakh. Cost incurred to date is Rs 120 lakh, which includes Rs 20 lakh of steel pu…
- Gupta Engineering Ltd began a contract for Rs 60 lakh. Contract costs incurred in the year were Rs 18 lakh, and the outcome cannot be estima…
- Shivalik Constructions Ltd has a fixed price contract of ₹1,000 lakh. At the year end, costs incurred to date are ₹480 lakh, which include ₹…
- Himalaya Projects Ltd has a fixed price contract of ₹500 lakh. At the end of the first year, costs incurred are ₹300 lakh and the estimated …