Navkar Infra Ltd is building a bridge under a fixed price contract. The contract does not specify that general administration costs are reimbursable by the customer. The company's accountant is listing the costs to include in contract costs under AS 7. Which of the following should be excluded from contract costs?
Head office general administration costs are excluded from contract costs because the contract does not provide for their reimbursement. AS 7 includes site costs, directly related design costs, and allocable insurance and depreciation, but treats unreimbursable administration, selling and R&D costs as period costs.
- ADepreciation of a crane used only on the bridge site
- BGeneral administration costs at head officeCorrect
- CCosts of designing and technical assistance directly related to the bridge
- DInsurance premium on the bridge site works
Explanation
AS 7 excludes general administration costs, selling costs and research and development costs unless reimbursement is specified in the contract. Here no reimbursement is specified, so head office administration costs are excluded. The other three items are directly attributable to the contract or are allocable insurance and depreciation, so they are included.
Did you get it right without looking?
One question tells you little. A timed set on AS 7 Construction Contracts shows your real accuracy, how long you take and where you lose marks.
More AS 7 Construction Contracts questions
- Konark Builders enters into a fixed price contract to construct a bridge for a contract price of ₹50,00,000. At the end of Year 1, costs inc…
- Rao Projects has a Rs 200 lakh fixed price contract. Cost incurred to date is Rs 120 lakh including Rs 20 lakh of steel purchased and delive…
- Malwa Constructions Ltd. has a contract for Rs 90 lakh. Up to the reporting date, costs incurred are Rs 54 lakh, which include Rs 6 lakh of …
- Sagar Constructions Ltd has a fixed price contract of ₹80 lakh. Estimated total cost is ₹60 lakh throughout the contract. Costs incurred are…
- At the year end, Kaveri Engineering Ltd has one contract in progress. Contract costs incurred to date are ₹900 lakh, recognised profits are …
- Tulsi Constructions Ltd. has a fixed price contract for Rs 120 lakh. At the end of Year 1, costs incurred are Rs 48 lakh and estimated costs…