CMA Final · Strategic Cost Management · Learning Curve
Rohan Machines builds an order of 8 special presses. The first press needs 1,000 labour hours and an 80% cumulative average time curve applies. Labour costs Rs 50 per hour. What is the labour cost of presses 5 to 8?
The labour cost of presses 5 to 8 is Rs 76,800. Total time for eight presses is 4,096 hours and for four presses 2,560 hours, so the last four take 1,536 hours. At Rs 50 per hour this gives Rs 76,800.
- ARs 76,800Correct
- BRs 1,28,000
- CRs 1,02,400
- DRs 2,04,800
Explanation
Average for 4 presses = 640 hours, total 2,560. Average for 8 presses = 512 hours, total 4,096. Presses 5-8 take 4,096 - 2,560 = 1,536 hours, costing 1,536 x 50 = Rs 76,800. Rs 1,28,000 is the cost of the first four presses, and Rs 2,04,800 is the cost of all eight.
Did you get it right without looking?
One question tells you little. A timed set on Learning Curve shows your real accuracy, how long you take and where you lose marks.
More Learning Curve questions
- Kavya Aerospace Pvt. Ltd. wins an order for 8 units. The first unit takes 1,000 hours and an 80% cumulative average curve applies. Labour is…
- Standard time for the first 4 units of a product was set using an 80% learning curve (cumulative average basis) with a first-unit time of 10…
- Sundaram Auto Components expects an 80% cumulative average time curve with a first-unit time of 100 hours. The standard time for units 9 to …
- Mehta Tools uses a 90% cumulative average-time learning curve for a new product. The first unit takes 200 hours. What are the total labour h…
- Ishaan Tools Ltd. applies an 80% incremental unit-time (Crawford) learning curve; the first unit takes 100 hours. Learning is expected to st…
- Kaveri Engineering observes that the first unit of a machine took 200 hours, and the first 4 units together took 648 hours. Assuming the cum…