CA Intermediate · Advanced Accounting · AS 7 Construction Contracts
Sagar Infra Ltd undertook a fixed price contract for Rs 80 lakh to build a warehouse for Kiran Traders. Costs incurred to date: Rs 30 lakh; estimated further cost to complete: Rs 30 lakh. Stage of completion is determined by the proportion of cost incurred to total estimated cost. What revenue should be recognised to date under AS 7?
Revenue recognised is Rs 40 lakh. The stage of completion is cost incurred Rs 30 lakh divided by total estimated cost Rs 60 lakh, which is 50 percent, and this is applied to the contract value of Rs 80 lakh under the percentage of completion method.
- ARs 30 lakh
- BRs 40 lakhCorrect
- CRs 60 lakh
- DRs 80 lakh
Explanation
Total estimated cost = 30 + 30 = Rs 60 lakh. Stage of completion = 30/60 = 50%. Revenue = 50% x 80 lakh = Rs 40 lakh. Rs 30 lakh is merely the cost incurred, not revenue.
Did you get it right without looking?
One question tells you little. A timed set on AS 7 Construction Contracts shows your real accuracy, how long you take and where you lose marks.
More AS 7 Construction Contracts questions
- Konkan Infra Ltd. entered into a fixed price contract with a State road corporation for Rs 80 lakh. Up to the reporting date, contract costs…
- Vindhya Infra Ltd has a fixed price contract of ₹80,00,000. At the end of Year 1: costs incurred ₹30,00,000, estimated further cost to compl…
- Himalaya Infra Ltd is building a bridge under a construction contract. Up to the reporting date it has incurred: direct materials ₹12,00,000…
- Konark Builders enters into a fixed price contract to construct a bridge for a contract price of ₹50,00,000. At the end of Year 1, costs inc…
- Rao Projects has a Rs 200 lakh fixed price contract. Cost incurred to date is Rs 120 lakh including Rs 20 lakh of steel purchased and delive…
- Malwa Constructions Ltd. has a contract for Rs 90 lakh. Up to the reporting date, costs incurred are Rs 54 lakh, which include Rs 6 lakh of …