CMA Final · Corporate Financial Reporting · Property, Plant and Equipment (Ind AS 16)
Sagar Textiles Ltd runs a spinning unit. Which of the following items, held by the company, meets the definition of property, plant and equipment under Ind AS 16?
A tangible machine held for production and expected to be used for several years is property, plant and equipment, because Ind AS 16 requires a tangible item held for use in production, rental or administration and expected to be used over more than one period.
- AA tangible machine held for production and expected to be used over several yearsCorrect
- BA tangible spare consumed fully within the current accounting period
- CStock of finished yarn held for sale in the ordinary course
- DA patent acquired to protect a spinning process
Explanation
Ind AS 16 defines PPE as tangible items held for production or supply of goods or services, rental or administrative purposes and expected to be used during more than one period. The machine satisfies both conditions. Yarn stock is inventory, the patent is intangible, and an item consumed within one period fails the more-than-one-period test.
Did you get it right without looking?
One question tells you little. A timed set on Property, Plant and Equipment (Ind AS 16) shows your real accuracy, how long you take and where you lose marks.
More Property, Plant and Equipment (Ind AS 16) questions
- Under Ind AS 16, which of the following tangible items meets the definition of property, plant and equipment?
- Which statement correctly describes how Ind AS 16 differs from IAS 16, according to the comparison in its Appendix 1?
- Which statement about Ind AS 16 and Ind AS 40 is correct, according to the Ind AS 16 text comparing it with IAS 16?
- Kaveri Engineering Ltd is evaluating a press for impairment. Its fair value less costs of disposal is ₹46 lakh and its value in use is ₹52 l…
- Kaveri Engineering Ltd estimates for a machine that it could currently sell the asset for ₹12,00,000 if it were already of the age and condi…
- Under Ind AS 16 as notified in India, a plant is being tested before it is ready for use. The plant produced sample units during testing, an…