CA Intermediate · Advanced Accounting · AS 16 Borrowing Costs
Sahyadri Infra Ltd. started constructing a bridge, a qualifying asset, on 1 April 2025 using a specific loan of Rs 1,20,00,000 at 10% p.a. Active development was suspended from 1 August 2025 to 30 November 2025 because of a prolonged dispute with the contractor over a design issue, which is not a necessary part of the normal construction process. Work resumed on 1 December 2025 and continued until 31 March 2026. Assume no other income on the loan funds. What amount of interest should be capitalised for the year ended 31 March 2026?
The amount to be capitalised is Rs 8,00,000. AS 16 requires capitalisation to be suspended during extended periods when active development is interrupted. Interest is Rs 1,00,000 per month, the four-month suspension is excluded, so eight months are capitalised, and the Rs 4,00,000 for the suspension is expensed.
- ARs 12,00,000
- BRs 8,00,000Correct
- CRs 4,00,000
- DRs 10,00,000
Explanation
Capitalisation must be suspended during extended periods when active development is interrupted, unless the delay is a necessary part of the process. Annual interest = 12,00,000, i.e. Rs 1,00,000 per month. The suspension covers 4 months (August to November), so the capitalised amount covers 8 months = Rs 8,00,000. Rs 12,00,000 ignores the suspension, and the remaining Rs 4,00,000 is charged to profit and loss.
Did you get it right without looking?
One question tells you little. A timed set on AS 16 Borrowing Costs shows your real accuracy, how long you take and where you lose marks.
More AS 16 Borrowing Costs questions
- Malabar Shipyards Ltd. borrowed ₹1,00,00,000 at 12% p.a. on 1 April 2025 specifically to build an office complex. Construction started on 1 …
- Konkan Textiles Ltd. began constructing a new dyeing unit on 1 April 2025. It borrowed Rs 2,00,00,000 specifically for the project at 9% p.a…
- Ganga Power Ltd. is building a power unit, a qualifying asset, from 1 April 2025. A specific loan of Rs 40,00,000 at 11% p.a. was taken on 1…
- Vindhya Engineering Ltd. is building a plant (a qualifying asset) financed from its general borrowings. During the year, the expenditure on …
- Meenakshi Pharma Ltd. took a specific loan of Rs 1,20,00,000 at 10% p.a. on 1 April 2025 to build a plant. Its general borrowings were Rs 80…
- Yamuna Textiles Ltd borrowed ₹10 crore at 9% p.a. specifically to build a new unit, which was under construction for the whole of 2025-26. P…