CA Intermediate · Cost and Management Accounting · Unit & Batch Costing
Sharma Components Ltd manufactures a part in batches. Per batch of 400 units, the set-up cost is Rs 6,000, and the material cost is Rs 90 per unit. Labour and overheads are Rs 40 per unit. The company sells at a profit of 20% on cost. What is the selling price per unit?
The selling price is Rs 174 per unit: cost of Rs 145 (15 set-up + 90 material + 40 labour and overheads) plus 20% profit on cost.
- ARs 156
- BRs 169.20
- CRs 174Correct
- DRs 195
Explanation
Set-up cost per unit = 6,000 / 400 = Rs 15. Total cost per unit = 15 + 90 + 40 = Rs 145. Profit at 20% on cost = 145 x 0.20 = Rs 29. Selling price per unit = 145 + 29 = Rs 174.
Did you get it right without looking?
One question tells you little. A timed set on Unit & Batch Costing shows your real accuracy, how long you take and where you lose marks.
More Unit & Batch Costing questions
- Which of the following is the most appropriate costing method for an industry such as a brick kiln or cement plant, where output consists of…
- Which of the following is a feature that distinguishes batch costing from job costing?
- Which of the following is a feature of batch costing as taught in Cost and Management Accounting?
- Shree Tools Ltd. makes components in batches. For a batch of 2,000 units, the set-up cost is Rs 12,000, direct materials Rs 90,000, direct l…
- Batch costing: a batch of 200 units has total cost Rs 84,000. During production 10 units were rejected as normal loss with no scrap value. W…
- In batch costing, if a batch of 1,000 units is completed and 40 units are found defective, which are reworked at a cost attributable to a sp…