Skip to content

CA Intermediate · Cost and Management Accounting · Unit & Batch Costing

Sharma Pens Ltd manufactures pens in batches. For a batch of 2,000 pens, the costs are: direct materials ₹40,000, direct wages ₹24,000, and factory overheads absorbed at 150% of direct wages. Administrative overheads are 10% of factory cost. What is the total cost per pen for this batch?

The cost per pen is ₹55. Factory overheads are ₹36,000, giving factory cost of ₹1,00,000. Adding administrative overheads of ₹10,000 (10% of factory cost) gives total cost of ₹1,10,000, which divided by 2,000 pens equals ₹55 per pen.

  1. A₹55.00Correct
  2. B₹50.00
  3. C₹49.60
  4. D₹60.50

Explanation

Factory overheads = 150% × 24,000 = 36,000. Factory cost = 40,000 + 24,000 + 36,000 = 1,00,000. Administrative overheads = 10% × 1,00,000 = 10,000. Total cost = 1,10,000; per pen = 1,10,000 / 2,000 = ₹55. Option ₹50 ignores administrative overheads.

Did you get it right without looking?

One question tells you little. A timed set on Unit & Batch Costing shows your real accuracy, how long you take and where you lose marks.

More Unit & Batch Costing questions