Shree Ganesh Bricks produces bricks. In a month, total cost was ₹9,00,000 for 1,50,000 good bricks. Costs include ₹60,000 of normal wastage cost already included in total cost and no other adjustments. A new customer asks for pricing at cost plus 20% on cost per good brick. What is the selling price per brick?
The selling price is ₹7.20 per brick. Normal wastage cost is already within the total cost of ₹9,00,000, so cost per good brick is ₹6. Adding a 20% markup on this cost gives ₹7.20.
- A₹6.00
- B₹7.20Correct
- C₹7.00
- D₹5.00
Explanation
Cost per good brick = 9,00,000 / 1,50,000 = ₹6, since normal wastage is already included in the total cost and is borne by good units. Selling price = 6 x 1.20 = ₹7.20. Deducting the wastage cost again would give a wrong cost of ₹5.60.
Did you get it right without looking?
One question tells you little. A timed set on Unit & Batch Costing shows your real accuracy, how long you take and where you lose marks.
More Unit & Batch Costing questions
- Under batch costing, the economic batch quantity (EBQ) is the batch size at which which of the following is minimised?
- Verma Engineering completes a batch of 800 units at a total cost of ₹4,00,000. It sells the batch at a profit of 25% on selling price. What …
- Kapoor Components makes a part in batches. Each batch has a set-up cost of ₹3,000, and the carrying cost is ₹4 per unit per year. Annual dem…
- Annual demand for a component is 7,200 units, produced in batches. Set-up cost is Rs 400 per batch and carrying cost is Rs 8 per unit per ye…
- A contractor-type unit costing case: Sundaram Textiles produced 4,000 metres of cloth. Costs: materials Rs 80,000, wages Rs 48,000, factory …
- Mehta Auto Components manufactures a part in batches. Annual demand is 24,000 units. Setup cost per batch is ₹1,500 and carrying cost is ₹4 …